Floyd Road and More South Cobb Construction Updates

Check out the latest updates on road constructions, delays and detours around Mableton, Austell and Cobb County from May 13 to 17.

Here are the latest updates on road work being done around Cobb County, according to the Cobb Department of Transportation. Clay Road to Hicks Road: Expect periodic lane closures 9 a.m.-4 p.m. Monday through Friday, with one lane remaining open. Pedestrian Access: Temporary sidewalks are in place are to assist pedestrians while crews install new sidewalks along the east side of Floyd Road. All existing CCT bus stops will be maintained during construction. Expect periodic lane closures with one lane remaining open in both directions between Austell Road to Powder Springs Road. Beginning May 28, Cobb SOT staff is scheduled to begin work replacing the existing, substandard, weight-restricted bridge on Hopkins Road over Wildhorse Creek. In …

Greg M

10:00 am on Monday, May 13, 2013

The updates on Floyd Road never seem to change it's the same updates. What we need is a projected time for completion.   more ›

Monday, May 6, 2013

South Cobb Road Work Updates, May 6-10

Before you start the week, check out the latest updates on road constructions, delays and detours around Cobb County.

Here are the latest updates on road work being done around Cobb County, according to the Cobb Department of Transportation. Expect periodic lane closures with one lane remaining open in both directions between Austell Road to Powder Springs Road. South Cobb Drive to Atlanta Road: Expect intermittent lane closures from 9 a.m. to 4 p.m. Monday through Friday, with one lane remaining open in each direction at all times.  Evelyn Street: The intersection with Concord Road will be permanently closed when the contractor begins work this Monday, May 6. Expect periodic lane closures from 9 a.m. to 4 p.m. Monday through Friday. One lane will remain open for your commute. Later this month, Cobb DOT will start replacing the bridge over Sope Creek on …

Monday, April 22, 2013

South Cobb Road Work Updates, April 22-26

Check out the latest updates on road constructions, delays and detours around South Cobb before you start the week.

Here are the latest updates on road work being done around Smyrna-Vinings and Cobb County, according to the Cobb Department of Transportation. Expect periodic lane closures with one lane remaining open in both directions between Austell Road to Powder Springs Road. Expect periodic lane closures from 9 a.m. to 4 p.m. Monday through Friday on Paper Mill Road at Sope Creek. One lane will remain open for your commute during the initial utility work. Starting in May, Cobb DOT will start replacing the bridge over Sope Creek on Paper Mill Road. The new bridge will include a six-foot sidewalk on the south side, providing access to the National Park Service trails. Paper Mill Road will be closed at the bridge for approximately four months. Signed …

Monday, March 25, 2013

South Cobb Road Work Updates, March 25-29

Check out the latest updates on road constructions, delays and detours around Austell, Mableton and Cobb County.

Here are the latest updates on road work being done around South Cobb and the county, according to Cobb Commissioners Bob Ott, Helen Goreham, Lisa Cupid, JoAnn Birrell and the Georgia Department of Transportation (GDOT). Expect periodic lane closures from 9 a.m. to 4 p.m., Monday through Friday, with one lane open for your commute. The contractor will be grading and placing concrete, and work on asphalt paving between Hyde Road and Asheforde Drive. Expect periodic lane closures from 9 a.m. to 4 p.m., Monday through Friday, with one lane remaining open for commute. Expect intermittent lane closures from 9 a.m. to 4 p.m., Monday through Friday, with one lane remaining open while the contractor continues grading, placing concrete sidewalk and…

Monday, February 18, 2013

Area Closures, Detours and Road Work Updates

Check out the latest updates on road constructions, delays and detours around Cobb County.

Here are the latest updates on road work being done around Cobb County, according to Commissioners Bob Ott, Helen Goreham, JoAnn Birrell and Lisa Cupid. Davidson Road to Willow Point Pkwy Willow Point Pkwy to Timber Ridge Road Karls Gate Drive to Lake Fjord Pass GDOT I-285 Top-End Resurfacing Project Expect delays as Georgia DOT continues working on a $56 million resurfacing project on I-285. Crews will resurface 10 miles of I-285 between Paces Ferry Road in Cobb County and Ashford Dunwoody Road in DeKalb County. Most work will take place nights and weekends. The project is scheduled to complete in August 2013. Click here for more information. Detour Scheduled for Multi-use Trail From Monday, Feb. 18, to Monday, March 11, parts of the …

Thursday, January 17, 2013

GDOT Issues Inclement Weather Road Advisory

GDOT is urging motorists to monitor weather conditions in advance with the possibility of light snow and icy roadways expected Thursday and Friday in areas of North Georgia.

Friday, June 15, 2012

UPDATE: Cobb to Hold Thursday Groundbreaking Event for Floyd Road Project

The project includes widening Floyd Road, constructing a median and the construction of a trail on one side of the road and a sidewalk on the other.

Floyd Road is being redesigned as a four-lane road with a 20-foot-wide raised median dividing the north and southbound lanes. The 20-foot-wide raised median will be similar to many of the same medians with the same widths throughout Cobb County, like the median along East West Connector, which is filled with trees, grass and bushes. James Hudgins, the pre-construction program manager for Cobb Department of Transportation, stated in an email, "The 20’ raised median will be equivalent to the raised median on the East-West Connector.   The 20’ raised median is a GDOT Standard, funded by GDOT, and follow GDOT standards." This is a direct quote from Hudgins, who helped handle the project details. Baldwin Paving will begin construction of the $5…

Patch_comments_icon

Kiri Walton

4:04 pm on Monday, June 18, 2012

This article has been updated. Also added are documents and maps and links all stating that there will be a 20-foot-wide median. Not sure if the words from the man overseeing the project details are not being believed or if it's the reporting by someone with a master's in community journalism of the words from the man overseeing the project details not being believed, but there will be a 20-foot-…   more ›